Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1040
Project Name: Sustainability Program FY18
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: This is a program of projects to strengthen VTA's commitment to the environment through conservation of natural resources, reduction of greenhouse gases, pollution prevention, and use of renewable energy/materials.
Status: In progress.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
51%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Dec-18 Jun-18 Jun-19 8%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1040
Project Name: Sustainability Program FY18
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $700 $700
Jul-17 Transfer from other VTA Transit Program project Transfer In/Out $354 $1,054