Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1045
Project Name: North SJ Transportation Improvements
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: Project would make transit capital improvements in North SJ using developer fees collected and retained by CSJ.
Status: Discussions have started with CSJ on potential scope.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-50%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1045
Project Name: North SJ Transportation Improvements
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $3,000 $3,000