Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1046
Project Name: Mobile Network Upgrade
Category: Information Sys & Technology
Project Location:
Systemwide
Project Scope and Status
Scope: Upgrade of mobile routers to provide passengers Wi-Fi connectivity to 130 buses and non-revenue vehicles.
Status: Procurement of mobile routes ongoing; PCMM opens bids on September 20 for 120 units of routers.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-18 2%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1046
Project Name: Mobile Network Upgrade
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $550 $550