Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1051
Project Name: SCADA Control Center & System Replacemen
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: The existing Control & Data Centers including existing SCADA system software and hardware are aging. This project will explore and recommend expansion options and design new Control and Data Centers to accommodate new SCADA System hardware and software.
Status: Funds to be secured.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-91%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1051
Project Name: SCADA Control Center & System Replacemen
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $3,769 $3,769