Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1055
Project Name: Roofing Management Program FY18
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: The project will fund two years of the roofing maintenance contract, pay for the manufacturer of the tent roof and supporting structure at Baypointe LRT Station Canopy to assess and recommend maintenance and work, and replace 3 roofs at Chaboya division.
Status: Not in design yet, not sure when design will begin due to previous commitment priorities.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Dec-19 Jun-19 Sep-19 2%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1055
Project Name: Roofing Management Program FY18
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $1,300 $1,300