Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0617
Project Name: SR 152 Realignment
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: Project includes improvements on SR 152 between US 101 and I-5. Improvements include realignment of SR 152 between US 101 and SR 156, eastbound truck climbing lanes & improvements @ SR 152/I-5 Interchange.
Status: Project Study Report-Project Development Support (PSR-PDS) document was approved on 4/30/2015. Once state funding is secured, Project Approval & Environmental Document (PA&ED) phase will begin.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-93%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
26%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0617
Project Name: SR 152 Realignment
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Apr-07 Initial Budget Setup $150 $150
Oct-07 Biennial Budget Adoption Augment $3,500 $3,650
Jul-09 Biennial Budget Adoption Augment $950 $4,600
Oct-10 Transfer from other VTP Highway Program project Transfer In/Out $1,000 $5,600
May-11 Transfer from other VTP Highway Program project Transfer In/Out $150 $5,750
Jul-11 Biennial Budget Adoption Augment $19,400 $25,150
May-13 Transfer from other VTP Highway Program project Transfer In/Out $1,250 $26,400
Jun-15 Transfer to other VTP Highway Program project Transfer In/Out -$143 $26,257
Jun-15 Transfer to other VTP Highway Program project Transfer In/Out -$1,015 $25,242
Jun-15 Transfer to other VTP Highway Program project Transfer In/Out -$452 $24,790
Jun-15 Biennial Budget Adoption Augment $6,600 $31,390