Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0788
Project Name: SR 237 Express Lanes-Phase II Extension
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: This project will convert the existing carpool lanes to Express Lanes between North First St in San Jose and Mathilda Ave in Sunnyvale. This project is Phase II of the SR 237 Express Lanes Project.
Status: Completed Project Approval/Environmental Document phase on 6/10/2015. Completed Final Designs. Project was advertised on 9/1/2017 and awarded on 12/8/2017. Construction Phase begins January 2018.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
5%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-14 Jan-18 Aug-19 48%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0788
Project Name: SR 237 Express Lanes-Phase II Extension
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-11 Initial Budget Setup $20,000 $20,000
Mar-12 Transfer from other VTP Highway Program project Transfer In/Out $50 $20,050
May-12 Transfer from other VTP Highway Program project Transfer In/Out $14 $20,064
Jul-12 Transfer from other VTP Highway Program project Transfer In/Out $3 $20,067
Apr-16 Transfer from other VTP Highway Program project Transfer In/Out $411 $20,478
Apr-16 Transfer from other VTP Highway Program project Transfer In/Out $500 $20,978
Jun-17 Biennial Budget Adoption Augment $18,022 $39,000
Nov-17 Transfer from other VTP Highway Program project Transfer In/Out $3,564 $42,564