Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0867
Project Name: US 101 / Buena Vista Avenue
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: The scope of work is to conduct preliminary engineering and planning for a new interchange at US 101 and Buena Vista Ave.
Status: Project is on hold and awaiting proposed land development adjacent to the future interchange.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-14%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-17 Jun-18 Jun-20 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0867
Project Name: US 101 / Buena Vista Avenue
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $1,000 $1,000
Jun-15 Biennial Budget Adoption Augment $3,000 $4,000