Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0901
Project Name: SV Express Lanes-US101/SR85 PH 4
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: Convert existing carpool lanes to Express Lanes on SR 85 (from US 101 in San Jose to SR 87) including conversion of US 101/SR 85 HOV connector south in San Jose and the approaches to/from US 101. | HOV=High Occupancy Vehicle
Status: Final design to begin in early 2018.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
111%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Dec-18 Nov-19 Nov-21 1%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0901
Project Name: SV Express Lanes-US101/SR85 PH 4
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Nov-14 Initial Budget Setup $3,000 $3,000
Jun-15 Biennial Budget Adoption Augment $8,400 $11,400
Jun-17 Biennial Budget Adoption Augment $12,600 $24,000