As of 12/31/2017
Program: VTP Highway
Project #: P-0972
Project Name: US101/Zanker Rd/Skyport Dr/N 4th St Inte
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: Project proposes to construct an overcrossing over US 101 from Zanker Road to Skyport Drive-N. Fourth Street and to modify existing on and off ramps to improve local access and multi-modal circulation to support the development area in North San Jose.
Status: Project Initiation Document (PID) Phase was completed in July 2017. Project Approval/Environmental Document (PA/ED) Phase began in late 2017 and is scheduled to be completed in early 2020.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
10%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Feb-19 Dec-21 May-23 1%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0972
Project Name: US101/Zanker Rd/Skyport Dr/N 4th St Inte
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $8,000 $8,000
Jun-17 Biennial Budget Adoption Augment $2,000 $10,000