Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0976
Project Name: I-680 Sound Walls
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: This project will construct soundwalls along I-680 between Capitol Expressway and Mueller Avenue in San Jose.
Status: Project Approval and Environmental Document (PA/ED) phase is ongoing and is expected to complete in April 2018. Design and construction phases will follow.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-75%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Apr-18 Sep-19 May-20 58%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0976
Project Name: I-680 Sound Walls
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $600 $600
Jun-17 Transfer from other VTP Highway Program project Transfer In/Out $500 $1,100
Jun-17 Biennial Budget Adoption Augment $4,900 $6,000