Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0978
Project Name: Countywide Bicycle Plan Update
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: Update of VTA's 2008 Countywide Bicycle Plan, with an emphasis on serving disadvantaged communities.
Status: July 2016 Initial public outreach.Fall 2016 Completed Cross County Bicycle Corridor updates.Nov 2016 VTA Board adopted Prioritization criteria.Summer 2017 Corridor prioritization w/staff recommendations released.Winter 2017/18 Draft plan for public review
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-16 Apr-18 61%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0978
Project Name: Countywide Bicycle Plan Update
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $700 $700