Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-0979
Project Name: Countywide Traffic Signal Coord. Study
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: Identify systematic approach & a project list to implement coordinated traffic signal system(s) that maximizes efficiency of existing traffic signal system infrastructure, improves multi-modal mobility & enhances integration & roadway network connectivity
Status: Staff will be reapplying for grants to fund this project. A local match of 20% of total project cost is typically required. The Call for Projects is anticipated in Summer 2017. The Award Notice is anticipated in Spring 2018.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-18 Jan-19 Jan-20 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0979
Project Name: Countywide Traffic Signal Coord. Study
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $170 $170