Program: VTP Highway
Project #: P-0981
Project Name: Bascom Corridor Complete Streets Study
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: Multi-jurisdictional complete streets study that will examine existing conditions, identify priorities for bicycle/pedestrian/transit riders, develop & analyze conceptual design alternatives & provide recommendations for funding & project implementation.
Status: Working with Member Agencies and evaluating design alternatives for the corridor. Also, Planning for the second round of public workshops in late 2017/early 2018.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-12%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-16 20%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0981
Project Name: Bascom Corridor Complete Streets Study
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $988 $988
Jun-16 Transfer from other VTP Highway Program project Transfer In/Out $31 $1,019
Jun-16 Transfer from other VTP Highway Program project Transfer In/Out $100 $1,119
Jun-17 Biennial Budget Adoption Augment $350 $1,469