Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-1060
Project Name: Traffic Analysis Software Procurement
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: The traffic analysis software procurement will replace an outdated software that is used by all member agencies and consultants in Santa Clara County to analyze transportation impacts from land use developments at signalized intersections.
Status: The Systems Operations & Management Working Group and VTA staff are currently evaluating potential softwares to replace the legacy traffic analysis software.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-1060
Project Name: Traffic Analysis Software Procurement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $145 $145