Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTP Highway
Project #: P-1061
Project Name: SR 237 Exp LN: Mathilda Ave to SR 85
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: Construct a new HOV/EL lane in both directions on SR 237 between Mathilda Ave. to SR 85, which includes modifications to the US 101/SR 237 interchange.
Status: Once funding is secured, Project Initiation Document (PID) Phase will begin. It is anticipated that this project will be constructed in phases.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-1061
Project Name: SR 237 Exp LN: Mathilda Ave to SR 85
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $2,000 $2,000