Project Scope and Status
Scope: Improve pedestrian safety and access to bus stops serving Berryessa BART. Include community outreach, environmental study & 35% PE design for construction of intersection improvemnts at selected intersections along King Rd. from Tully Rd. to Berryessa Rd.
Status: VTA is actively seeking outside grant funding to begin the project.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-1062
Project Name: King Rd Ped Safety/Transit Access Improv
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $686 $686