Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: 2000 Measure A
Project #: P-0967
Project Name: De Anza College Transit Ctr Improvements
Category: Bus Program
Project Location:
See Map
Project Scope and Status
Scope: Design and build a new transit center at De Anza College to accommodate additional buses. Project could also include an interim facility.
Status: Final design in progress for interim facility. Easement agreement approved by Foothill De Anza College Board of Trustees in October 2016. Construction to begin July 2017, with construction completion and bus stop opening in Fall 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-26%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Aug-15 Jun-16 Dec-21 4%
Budget History ($ in thousands) Budget History Glossary
Program: 2000 Measure A
Project #: P-0967
Project Name: De Anza College Transit Ctr Improvements
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $10,000 $10,000
Jun-16 Transfer to other 2000 Measure A Program project Transfer In/Out -$669 $9,331
Dec-16 Transfer to other 2000 Measure A Program project Transfer In/Out -$1,600 $7,731
Jul-17 Transfer to other 2000 Measure A Program project Transfer In/Out -$300 $7,431
Oct-17 Transfer from other 2000 Measure A Program project Admin Allocation $3 $7,435