As of 12/31/2017
Program: 2000 Measure A
Project #: P-0992
Project Name: Berryessa Garage Solar Panel System
Category: SVRT Program
Project Location:
Systemwide
Project Scope and Status
Scope: Install a 152kW-DC solar photovoltaic system (solar) on the roof of the Berryessa Station parking garage, adjacent to the future BART station, located between Berryessa and Mabury roads in San Jose.
Status: A change order was issued to McCarthy Builders (C730 - SVBX Parking Garages) and the contractor has completed solar panel installation. Minor monitoring costs will accrue until SVBX Revenue Service.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Feb-16 Apr-16 Dec-16 89%
Budget History ($ in thousands) Budget History Glossary
Program: 2000 Measure A
Project #: P-0992
Project Name: Berryessa Garage Solar Panel System
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Apr-16 Initial Budget Setup $2,000 $2,000