Home>Transparency>Open Data>Project Scope, Status, Cost and Budget
Project Scope, Status, Cost and Budget
Project Scope, Status, Cost and Budget
As of 12/31/2017Program: | 2000 Measure A |
Project #: | P-0998 |
Project Name: | Rapid 523 Bus Stop Improvements |
Category: | Bus Program |
Project Location: |
|
Project Scope and Status
Scope: Project will complete the design phase of Rapid 523 and provide enhanced stops with new shelter, seating, lighting and other associated bus stop improvements. |
Status: Design completed and the contract was initially advertised in November 2016 but all bids were rejected. Re-bid of the construction contract completed and was awarded by VTA Board in April 2017. Field work started & planned to complete in spring 2018. |
Project Cost and Budget
Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%
0%
|
|
No Indicator: Percentage is within +10% and -10% tolerance. |
Project Milestones
Milestone Glossary
Design Start |
Construction/ Procurement Start |
Construction/ Procurement Complete |
Percent Complete |
---|---|---|---|
Jan-16 | Apr-17 | Apr-18 | 55% |
Budget History ($ in thousands)
Budget History Glossary
Program: | 2000 Measure A |
Project #: | P-0998 |
Project Name: | Rapid 523 Bus Stop Improvements |
Date | Budget Change Description | Change Type | Amount |
Cumulative Total Appropriation |
---|---|---|---|---|
Jun-16 | Initial Budget Setup | $3,900 | $3,900 | |
Apr-17 | Transfer from other 2000 Measure A Program project | Admin Allocation | $1 | $3,901 |
Jul-17 | Transfer from other 2000 Measure A Program project | Admin Allocation | $2 | $3,903 |
Oct-17 | Transfer from other 2000 Measure A Program project | Admin Allocation | $5 | $3,907 |