Timeline/Calendar
|
Future |
| 2016 |
Begin service: US 101 Express Lanes
|
| 2015 |
Begin service: 237 Express Lanes, Phase II |
| 2014 |
Begin service: SR 85 Express Lanes
|
|
|
|
|
|
SR 237 Express Lanes Schedule |
| 2012 |
March 20 - SR 237 Express Lanes open |
|
Late January - Painted buffering |
|
|
| 2011 |
Fall/Winter - Electronic Toll System installation |
|
Fall - Roadway construction begins |
|
June - VTA Board authorizes awarding of construction contract |
|
June - VTA Board reviews operational procedures |
|
Spring - Environmental and final design approval |
|
March 7 - Public meeting held at VTA |
|
March - VTA Board approved signage structure procurement |
|
Feb. - VTA Board committees receive project updates
|
|
|
|
|
|
Previous Years |
| 2010 |
Begin service: I-680 Express Lanes in Alameda & Santa Clara Counties |
| 2009 |
Continue Environmental Clearance for SR 85/US 101 Express Lanes Project |
| 2009 |
Begin traffic/design analysis for the SR 237 Express Connector Project |
| 2008 |
VTA Board approves Silicon Valley Express Lanes Program Implementation Plan
|
| 2008 |
SR 85 Preliminary Engineering and Public Outreach
|
| 2007 |
Legislative Authority – AB 574 |
| 2005 |
VTA Feasibility Study |
| 2004 |
Legislative Authority – AB 2032 |
| 2003 |
VTA Ad Hoc Financial Stability Committee Recommendation |
|
|
|
|