BOARD MEMORANDUM
| TO: |
Bicycle and Pedestrian Advisory Committee |
|   | Santa Clara Valley Transportation Aurthority |
|   | Board of Directors |
|   |   | | THROUGH: | Suzanne B. Gifford |
|   | General Manager Pro Tempore |
|   |   | | FROM: | Carolyn M. Gonot |
|   | Chief Development Officer |
|   |   |
| SUBJECT: |
Programmed Projects Quarterly Monitoring Report from April through June 2005 |
FOR INFORMATION ONLY
Every quarter, the
Programmed Projects Quarterly Monitoring Report is presented to the VTA Board of
Directors and the VTA Policy and Technical Advisory Committees. The
objective of the report is to assist VTA staff, the Advisory Committees, the
Board of Directors and project sponsors in tracking progress of the projects
funded through programming actions of the VTA Board. The last report
was presented to the VTA Board on May 5, 2005.
The Programmed
Projects Quarterly Monitoring Report from April through June 2005 is attached
for your review. This report provides the current status on
discretionary funded projects.
A project summary
sheet highlighting projects with funds expiring in 2005 is also
attached.
The project summary
sheet identifies projects in three categories:
- Red – Projects at the risk of losing
funds due to delivery difficulties.
- Yellow – Projects that may need extra
attention or will risk running into difficulties.
- Green – Project is progressing smoothly.
The next Programmed
Projects Quarterly Monitoring Report will be prepared for the quarter between
July and September 2005.
| Prepared by: | John Sighamony, Transportation Planner III |
|   |   |