Agenda Item # 8
| |
Date: |
July 29, 2005 |
| |
Committee Meeting Date: |
August 11, 2005 |
| |
Board Meeting Date: |
September 1, 2005 |
| |
ACTION
___
     DISCUSSION
___
| INFO  
X
|
BOARD MEMORANDUM
| TO: |
Policy Advisory Committee |
|   | Santa Clara Valley Transportation Authority |
|   | Board of Directors |
|   |   | | THROUGH: | Suzanne B. Gifford |
|   | General Manager Pro Tempore |
|   |   | | FROM: | Carolyn M. Gonot |
|   | Chief Development Officer |
|   |   |
| SUBJECT: |
Programmed Projects Quarterly Monitoring Report from April through June 2005 |
FOR INFORMATION ONLY
The Programmed Projects Quarterly Monitoring Report from April through June 2005 is attached for your review. This report provides the current status on discretionary funded projects.
A project summary sheet highlighting projects with funds expiring in 2005 is also attached.
The project summary sheet identifies projects in three categories:
- Red – Projects at the risk of losing funds due to delivery difficulties.
- Yellow – Projects that may need extra attention or will risk running into difficulties.
- Green – Project is progressing smoothly.
The next Programmed Projects Quarterly Monitoring Report will be prepared for the quarter between July and September 2005.
| Prepared by: | John Sighamony, Transportation Planner II |
|   |   |