Transit Planning and Operations
Thursday, August 19, 2004
4:30 PM
City of San Jose
801 North First Street - Room 106E
San Jose, California
Summary Minutes
|
1. |
CALLED TO ORDER at 4:34 p.m.
ROLL CALL
|
Members Present
|
Members Absent
|
|
David Cortese, Chairperson
|
Pete McHugh
|
|
Ron Gonzales
|
Joe Pirzynski, Vice Chairperson
|
|
|
|
| Alternates Present |
Alternates Absent |
|
None
|
Blanca Alvarado
|
|
|
Dolores Sandoval
|
|
|
Ken Yeager
|
*Alternates do not serve unless participating as a Member.
A quorum was not present and a Committee of the Whole was declared.
| |   |   |
|
2. |
PUBLIC PRESENTATIONS
There were no Public Presentations.
| |   |   |
|
3. |
ORDERS OF THE DAY
There were no Orders of the Day.
| |   |   |
CONSENT AGENDA |
|
4. |
The Committee of the Whole deferred the Minutes of May 20, 2004.
| |   |   |
|
5. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to authorize the General Manager to execute a contract with Stacy and Witbeck, Inc., the lowest responsible bidder, in an amount of $878,068 for construction of the Vasona Light Rail Project San Fernando Station Plaza. This contract is 81 percent federally funded.
| |   |   |
|
6. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to authorize the General Manager to amend the total authorized funding for the Stacy and Witbeck, Inc., construction contract to accommodate the final contract close-out adjustments on the Tasman East Light Rail Project – Civil, Track and Landscaping (I-880 to Hostetter) contract in an amount of $132,000, for a new authorized amount of $22,856,559.
| |   |   |
|
7. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to approve the concept proposal for artist Masayuki Nagase’s Bench “Sculptures” CODE project at the Palo Alto Caltrain Transit Center.
| |   |   |
|
8. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to authorize the General Manager to execute a contract with Harsco Track Technologies for light rail grinding and profiling of VTA’s light rail track at a cost of $621,250 for a three-year period.
| |   |   |
|
9. |
The Committee of the Whole received the Community Oriented Design Enhancements (CODE) Program Update – July through August 2004.
| |   |   |
|
10. |
The Committee of the Whole received the Report on the Vasona Light Rail Project for the Month of July 2004.
| |   |   |
|
11. |
The Committee of the Whole received the Joint Powers Board Monthly Status Report.
| |   |   |
|
12. |
The Committee of the Whole received the Committee for Transit Accessibility Report.
| |   |   |
|
13. |
The Committee of the Whole received the Monthly Legislative Reports.
| |   |   |
REGULAR AGENDA |
|
14. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to authorize the General Manager to execute task order contracts with five civil engineering, three architectural, and two electrical engineering consultant firms for General Engineering and Architectural Consultant Services for facilities, rail, and highway projects services to be utilized on an as-needed basis. Each contract will be for a period of up to three years, with an option to extend the contract for an additional two-year term. The total amount for all ten contracts will not exceed $10,000,000.
| |   |   |
|
15. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to authorize the General Manager to execute a contract with Valley Transit Consultants for Preliminary Engineering services on the Downtown East Valley – Capitol Expressway Light Rail Project in an amount not to exceed $10,400,000. The initial contract term will be for 13 months. This contract is currently locally funded.
| |   |   |
|
16. |
The Committee of the Whole approved submitting a recommendation to the Board of Directors to authorize the General Manager to amend the contract with EIP Associates, Inc., for the preparation of the Environmental Impact Statement/Environmental Impact Report (EIS/EIR) for the Downtown East Valley Santa Clara/Alum Rock Corridor Project, increasing the approved contract value by $165,000 for a new contract value not to exceed $902,834.
| |   |   |
OTHER ITEMS |
|
17. |
The Committee of the Whole reviewed the Committee Work Plan.
| |   |   |
|
18. |
Committee Staff Report
There was no Committee Staff Report.
| |   |   |
|
19. |
Chairperson’s Report
There was no Chairperson’s Report.
| |   |   |
|
20. |
The Committee of the Whole determined the Consent Agenda for the September 2, 2004 Board Meeting.
CONSENT: Item #5. Authorize the General Manager to execute a contract with Stacy and Witbeck, Inc., the lowest responsible bidder, in an amount of $878,068 for construction of the Vasona Light Rail Project San Fernando Station Plaza. This contract is 81 percent federally funded; Item #6. Authorize the General Manager to amend the total authorized funding for the Stacy and Witbeck, Inc., construction contract to accommodate the final contract close-out adjustments on the Tasman East Light Rail Project – Civil, Track and Landscaping (I-880 to Hostetter) contract in an amount of $132,000, for a new authorized amount of $22,856,559; Item #7. Approve the concept proposal for artist Masayuki Nagase’s Bench “Sculptures” CODE project at the Palo Alto Caltrain Transit Center; Item #8. Authorize the General Manager to execute a contract with Harsco Track Technologies for light rail grinding and profiling of VTA’s light rail track at a cost of $621,250 for a three-year period; Item #14. Authorize the General Manager to execute task order contracts with five civil engineering, three architectural, and two electrical engineering consultant firms for General Engineering and Architectural Consultant Services for facilities, rail, and highway projects services to be utilized on an as-needed basis. Each contract will be for a period of up to three years, with an option to extend the contract for an additional two-year term. The total amount for all ten contracts will not exceed $10,000,000; Item #15. Authorize the General Manager to execute a contract with Valley Transit Consultants for Preliminary Engineering services on the Downtown East Valley – Capitol Expressway Light Rail Project in an amount not to exceed $10,400,000. The initial contract term will be for 13 months. This contract is currently locally funded; and Item #16. Authorize the General Manager to amend the contract with EIP Associates, Inc., for the preparation of the Environmental Impact Statement/Environmental Impact Report (EIS/EIR) for the Downtown East Valley Santa Clara/Alum Rock Corridor Project, increasing the approved contract value by $165,000 for a new contract value not to exceed $902,834.
| |   |   |
|
21. |
Announcements
There were no Announcements.
| |   |   |
|
22. |
Adjourned at 4:38 p.m.
| |   |   |
|
|