County of Santa Clara Board of Supervisors and VTA Board of Directors Receive Status Reports and/or Consider Budget Adjustments Regarding the 1996 Measure B Transportation Improvement Program
A. Community Oriented Design Enhancement (CODE) Program and 1996 Measure B Consolidated Biological Mitigation Site
The Agenda was taken Out of Order.
2. Consolidated Biological Mitigation Site: Decrease budget from $6.9 million to $5.9 million.
VTA Board Member Pat Dando requested clarification of the Consolidated Biological Mitigation Site. Mr. Funk explained that it is a site for habitat establishment for lost habitation from Rail and Highway Projects as part of the Program.
VTA Board Member Pat Dando queried if and recommended VTA consider a partnership for a mitigation site that other entities can buy into.
Action:
M/S/C (Williams/McLemore) for the VTA Board of Directors to approve the amendment of the Budget Adjustments regarding the 1996 Measure B Transportation Improvement to decrease budget from $6.9 million to $5.9 million.
M/S/C (Beall/Gage) for the County of Santa Clara Board of Supervisors to approve the amendment of the Budget Adjustments regarding the 1996 Measure B Transportation Improvement to decrease budget from $6.9 million to $5.9 million.
1. CODE Program: Increase budget from $7.2 million to $7.3 million.
Action:
M/S/C (Williams/McLemore) for the VTA Board of Directors to approve the amendment to the Budget Adjustments regarding the 1996 Measure B Transportation Improvements to increase budget from $7.2 million to $7.3 million.
M/S/C (Beall/Gage) for the County of Santa Clara Board of Supervisors to approve the amendment to the Budget Adjustments regarding the 1996 Measure B Transportation Improvements to increase budget from $7.2 million to $7.3 million.
B. HighwayProgram
Mr. Funk noted that changes are up and down for a variety of reasons, noting soft-cost changes are due to the new methodology that VTA has implemented for overhead recovery on Capital Project delivery.
Action:
M/S/C (Gonzales/Williams) for the VTA Board of Directors to approve the amendment to:
1) Route 880 Widening: Increase budget from $73.9 million to $76.3 million
2) Route 101 Widening: Increase budget from $54.2 million to $55.2 million
3) Route 85/101 (S): Increase budget from $65.8 million to $66.8 million
4) Route 85/87 Interchange: Decrease budget from $44.3 million to $42.8 million
5) Route 85/101 (N): Decrease budget from $124.2 million to $122.6 million
6) Route 237/880 Interchange: Support the request from the City of Milpitas to increase the budget of the Measure B 237/880 Interchange Project by $62,500 to share in the cost of completing road repairs on Calaveras Boulevard as a result, in part, of the Measure B interchange projects construction
7) Route 17 Improvements: Decrease budget from $12.9 million to $11.8 million
8) Route 87 (S) HOV Lanes: Increase budget from $14.5 million to $15.1 million
9) Route 87 (N) HOV Lanes: Increase budget from $10.5 million to $11.0 million
10) Route 152 Improvements: Increase budget from $15.0 million to $21.9 million
11) Route 85 Noise Mitigation: Decrease budget from $1.2 million to $1.2 million
Mr. Davis clarified that the Motion includes the recommendation to Item #6.B.6. to support staffs recommendation to support the request from the City of Milpitas to increase the budget of the Measure B 237/880 Interchange Project by $62,500 to share in the cost of completing road repairs on Calaveras Avenue as a result, in part, of the Measure B Interchange Projects construction.
M/S/C (Beall/Gage) for the Board of Supervisors to approve the amendment to:
1) Route 880 Widening: Increase budget from $73.9 million to $76.3 million
2) Route 101 Widening: Increase budget from $54.2 million to $55.2 million
3) Route 85/101 (S): Increase budget from $65.8 million to $66.8 million
4) Route 85/87 Interchange: Decrease budget from $44.3 million to $42.8 million
5) Route 85/101 (N): Decrease budget from $124.2 million to $122.6 million
6) Route 237/880 Interchange: Support the request from the City of Milpitas to increase the budget of the Measure B 237/880 Interchange Project by $62,500 to share in the cost of completing road repairs on Calaveras Boulevard as a result, in part, of the Measure B interchange projects construction
7) Route 17 Improvements: Decrease budget from $12.9 million to $11.8 million
8) Route 87 (S) HOV Lanes: Increase budget from $14.5 million to $15.1million
9) Route 87 (N) HOV Lanes: Increase budget from $10.5 million to $11.0 million
10) Route 152 Improvements: Increase budget from $15.0 million to $21.9 million
11) Route 85 Noise Mitigation: Decrease budget from $1.2 million to $1.2 million
Board of Supervisors Chairperson and VTA Board Member Pete McHugh thanked staff for the recommendation regarding Item 6.B.6., Route 237/880 Interchange.
C. Rail Program
Action:
M/S/C (Cortese/Williams) for the VTA Board of Directors to approve the amendment to:
1) Tasman East Light Rail: Decrease budget from $282.4 million to $275.1 million
2) Capital Light Rail: Decrease budget from $166.5 million to $159.8 million
3) Vasona Light Rail: Decrease budget from $320.4 million to $316.8 million
4) Caltrain Service Improvements: Decrease budget from $54.2 million to $52.2 million
M/S/C (McHugh/Beall) for the County of Santa Clara Board of Supervisors to approve the amendment to:
1) Tasman East Light Rail: Decrease budget from $282.4 million to $275.1 million
2) Capital Light Rail: Decrease budget from $166.5 million to $159.8 million
3) Vasona Light Rail: Decrease budget from $320.4 million to $316.8 million
4) Caltrain Service Improvements: Decrease budget from $54.2 million to $52.2 million
D. Other Programs
1. Bicycle Program
Carolyn Gonot, VTA Chief Development Officer, stated that Measure B Funds have been used to fund the Tier 1 Bicycle Program and the allocations of funds are noted in a Table in the FY 2005 Revenue and Expenditure Plan.
Ms. Gonot noted that there is one update to the VTA Pilot Parking Program, which was not listed in the Table and that is the funding for the bicycle parking at the VTA Light Rail Stations and Caltrain Stations.
On order of Chairperson Gage, there being no objection, the Bicycle Program Progress Report was received.
2. Pavement Management Program
Ms. Gonot noted that the Pavement Management Program has been fully expended with the $90 million allocated to each of the cities.
On order of Chairperson Gage, there being no objection, the Pavement Management Program was received.
3. Swap Projects: Exchange $22.5 million in State Transportation Improvement Program (STIP) funding for the Route 237/880 Stage C project in exchange for an equal amount of Measure B funding to be returned to VTA; reimburse VTA $7.23 million for costs incurred for landscaping for the following four Measure B projects: 1) Route 880 Widening, 2) Route 237/880 Interchange Stage C, 3) Route 85/101 (N) Interchange, and 4) Route 87 (N/S) High Occupancy Vehicle (HOV) lanes.
John Ristow, VTA Deputy Director Programming & Highway Administration, noted that Item 6.D.3.3., Route 85/101 (N) Interchange is a continuation of programming where federal and state money from VTA is swapped to certain Measure B projects which then would release local funds for use for pavement management and a number of other projects.
Action:
M/S/C (Gonzales/Pirzynski) for the VTA Board of Directors to approve the amendment to Swap Projects: Exchange $22.5 million in State Transportation Improvement Program (STIP) funding for the Route 237/880 Stage C project in exchange for an equal amount of Measure B funding to be returned to VTA; reimburse VTA $7.23 million for costs incurred for landscaping for the following four Measure B projects: 1) Route 880 Widening, 2) Route 237/880 Interchange Stage C, 3) Route 85/101 (N) Interchange, and 4) Route 87 (N/S) High Occupancy Vehicle (HOV) lanes.
Santa Clara County Board of Supervisor and VTA Ex-Officio Board Member Jim Beall requested staff consider using bicycle funds and other funds to possible use as matching funds to get other grant fund and requested if staff is successful in doing so and to report to both Boards as to the successes.
M/S/C (Beall/Gage) for the County of Santa Clara Board of Supervisors to approve the amendment to Swap Projects: Exchange $22.5 million in State Transportation Improvement Program (STIP) funding for the Route 237/880 Stage C project in exchange for an equal amount of Measure B funding to be returned to VTA; reimburse VTA $7.23 million for costs incurred for landscaping for the following four Measure B projects: 1) Route 880 Widening, 2) Route 237/880 Interchange Stage C, 3) Route 85/101 (N) Interchange, and 4) Route 87 (N/S) High Occupancy Vehicle (HOV) lanes.
4. Level of Service Intersection Improvement Program
Michael Murdter, Director County of Santa Clara County Roads and Airports, noted that the Program is moving forward and there are no proposed budget modifications to the Program.
With regard to the Intersection Level of Service Program, Mr. Murdter reported that the Montague Expressway Project will be agendized for award by the Santa Clara County Board of Supervisors on June 22, 2004, Central Expressway will begin construction soon; Almaden Expressway should benefit from the reprogramming action taken by the VTA Board of Directors; San Tomas Expressway at Campbell Avenue is complete; and, Foothill Expressway Project is underway.
On order of Chairperson Gage, there being no objection, the Level of Service Intersection Improvement Program Progress Report was received.
5. Expressway Signal Synchronization Program
Mr. Murdter noted that the Program is moving foward and there are no proposed budget modifications to the Program.
Mr. Murdter reported that Central Expressway, Lawrence Expressway, Oregon Expressway and Page Mill Expressway segments are complete. Foothill Expressway and Almaden Expressway are under way and the hardware and software upgrades for the Traffic Operation Center.
On order of Chairperson Gage, there being no objection, the Expressway Signal Synchronization Program Progress Report was received.
|