County of Santa Clara Board of Supervisors and VTA Board of Directors Receive Status Reports and/or Consider Budget Adjustments Regarding the 1996 Measure B Transportation Improvement Program
- Community Oriented Design Enhancement (CODE) Program and 1996 Measure B Consolidated Biological Mitigation Site
1. CODE Program: Decrease budget from $7.3 million to $6.8 million.
Action:
M/S/C (Williams/Kniss) for VTA Board of Directors to approve the amendment to the Budget Adjustments regarding the 1996 Measure B Transportation Improvements to decrease budget from $7.3 million to $6.8 million.
NOTE: M/S/C MEANS MOTION SECONDED AND, UNLESS OTHERWISE INDICATED, THE MOTION PASSES UNANIMOUSLY.
Margaret Okuzumi, Executive Director BayRail Alliance, expressed concern that the original allocation for Caltrain in the 1996 Measure B Transportation Improvement Program was $88 million and expressed that she is gratified to learn that on behalf of her organization the California Avenue Underpass has been identified as the most significant improvement to improve Caltrain service for the riders, improve safety, and access.
M/S/C (McHugh/Gage) for Santa Clara County Board of Supervisors and VTA Board of Directors receive Status Reports and/or Consider Budget Adjustments regarding the 1996 Measure B Transportation Improvement Program.
2. Consolidated Biological: Mitigation Site: Increase budget from $6.6 million to $7.3 million.
Action:
M/S/C (Williams/Kniss) for VTA Board of Directors to approve the amendment of the Budget Adjustments regarding the 1996 Measure B Transportation Improvement to increase budget from $6.6 million to $7.3 million.
M/S/C (McHugh/Gage) for Santa Clara County Board of Supervisors to approve the amendment of the Budget Adjustments regarding the 1996 Measure B Transportation Improvement to increase budget from $6.6 million to $7.3 million
B. Highway Program
Action:
M/S/C (Williams/Chu) for VTA Board of Directors to approve the amendment to:
1. Route 880 Widening: Increase budget by $35,000 from $76.1 million to $76.1 million.
2. Route 101 Widening: Decrease budget from $55.3 million to $54.5 million.
3. Route 85/101 (S): Increase budget from $67.7 million to $68.4 million.
4.Route 85/87 Interchange: Increase budget by $22,000 from $43.1 million to $43.1 million.
5. Route 85/101 (N): Increase budget from $123.4 million to $125.3 million.
6. Route 237/880 Interchange: Increase budget from $50.0 million to $51.2 million.
7. Route 17 Improvements: Increase budget from $26.8 million to $28.2 million.
8. Route 87 (S) HOV Lanes: Increase budget from $15.1 million to $15.5 million.
9. Route 87 (N) HOV Lanes: Decrease budget by $16,000 from $11.0 million to $11.0 million.
10. Route 152 Improvements: Increase budget from $22.0 million to $22.7 million.
11. Route 85 Noise Mitigation: Decrease budget from $9.3 million to $9.0 million.
M/S/C (McHugh/Gage) for Santa Clara County Board of Supervisors to approve the amendment to:
1. Route 880 Widening: Increase budget by $16,000 from $76.1 million to $76.1 million.
2. Route 101 Widening: Decrease budget from $55.3 million to$54.5 million.
3. Route 85/101 (S): Increase budget from $67.7 million to $68.4 million.
4. Route 85/87 Interchange: Increase budget by $22,000 from $43.1 million to $43.1 million.
5. Route 85/101 (N): Increase budget from $123.4 million to $125.3 million.
6. Route 237/880 Interchange: Increase budget from $50.0 million to $51.2 million.
7. Route 17 Improvements: Increase budget from $26.8 million to $28.2 million.
8. Route 87 (S) HOV Lanes: Increase budget from $15.1 million to $15.5 million.
9. Route 87 (N) HOV Lanes: Decrease budget by $16,000 from $11.0 million to $11.0 million.
10. Route 152 Improvements: Increase budget from $22.0 million to $22.7 million.
11.Route 85 Noise Mitigation: Decrease budget from $9.3 million to $9.0 million.
C. Rail Program
Action:
M/S/C (Cortese/Williams) for VTA Board of Directors to approve the amendment to:
1.Tasman East Light Rail: Decrease budget from $273.1 million to $272.8 million.
2. Capital Light Rail: Decrease budget from $159.8 million to $156.8 million.
3. Vasona Light Rail: Decrease budget from $317.2 million to $314.7 million.
4. Caltrain Service Improvements: Increase budget from $52.7 million to $54.3 million.
M/S/C (McHugh/Gage) for the Santa Clara County Board of Supervisors to approve the amendment to:
1.Tasman East Light Rail: Decrease budget from $273.1 million to $272.8 million.
2.Capitol Light Rail: Decrease budget from $159.8 million to $156.8 million.
3.Vasona Light Rail: Decrease budget from $317.2 million to $314.7 million.
4.Caltrain Service Improvements: Decrease budget from $52.7 million to $54.3 million.
D. Other Programs
1. Bicycle Program
John Ristow, Deputy Director Programming and Highway Administration, stated that all projects in the Bicycle Program are moving forward in the planning and design phases contingent upon construction funding from additional state and federal sources. Mr. Ristow noted that the most significant accomplishment in the Bicycle Program is the River Oaks Bridge. The bridge will start construction mid-June 2005 and will link Santa Clara and the Rivermark Development with the light rail station in San Jose.
On order of Chairperson Pirzynski, there being no objection, the Bicycle Program Progress Report was received.
2. Pavement Management Program
Mr. Ristow stated that there was no activity last year as, all projects were completed.
On order of Chairperson Pirzynski, there being no objection, the Pavement Management Program was received.
3. Swap Projects: Mr. Ristow stated that there were no new Swap Projects last year and no new future Swaps are anticipated for the Pavement Management Program.
Action: None
- Level of Service Intersection Improvement Program
Board Member Gonzales inquired as to SB 1233 regarding bicycle access to the expressway system.
Michael Murdter, Director Santa Clara County Roads and Airports, noted that SB 1233 has no effect on bicycle access to the expressway system. In Santa Clara County expressways are being restriped to better accommodate bicyclists. The language in SB1233 allows cities and the County to restrict and prohibit pedestrian access in areas where there is lack of sidewalks and no space behind the curb for pedestrians to safely walk. This enables cities and the County to jointly enact pedestrian prohibitions until it is safe for pedestrians to access those areas. The language is related to pedestrian access and not intended for bicyclists.
With regard to the Intersection Level of Service Program, Mr. Murdter reported that the Montague Expressway Project and Central Expressway Project are under construction with completion slated for 2006.
On order of Chairperson Pirzynski, there being no objection, the Level of Service Intersection Improvement Program Progress Report was received.
5. Expressway Signal Synchronization Program
Mr. Murdter noted that the Express Signal Synchronization Program (ESS) is moving foward and there are no proposed budget modifications to the Program.
On order of Chairperson Pirzynski, there being no objection, the Expressway Signal Synchronization Program Progress Report was received.
Member Gage and Chairperson Pirzynski thanked VTA staff for their hard work, diligence, and dedication on the reports submitted. Chairperson Pirzynski expressed kudos to both Boards and extraordinary VTA staff.
|