Customer Service Photo

Contact Me


Customer Service

(408) 321-2300

customer.service@vta.org


Evelyn Demolition Update

Mountain View Light Rail Double Track Project Update

May 1, 2015

Inquiries regarding this project should be directed to:
VTA Community Outreach
community.outreach@vta.org
(408) 321-7575

 

Evelyn Station Demolition Continues

The Mountain View Light Rail Double Track Project met a major milestone last weekend when the contractor finished the demolition of the main Evelyn Station passenger platform.

Although the progress is significant, VTA recognizes that nearby residents are still experiencing the noise created by nighttime demolition activities. VTA has taken the following actions to reduce noise impacts:

  • VTA construction inspectors are analyzing data from monitoring devices to address any instances of excessive noise level generation.
  • VTA has revised the scope of work to eliminate most demolition of concrete located below ground level.  

The current contractor’s schedule shows concrete demolition activities continuing through May 17, 2015 but with the reduced scope of work noted above, completion is anticipated earlier. VTA is committed to delivering the Mountain View Light Rail Double Track Project in a safe and efficient manner and thanks you for your continued patience.

Connect
With Us:

Trip Planner



Notices & Service Alerts

Last update: 01/19/2018

Bus Bridge due to Rail Construction at Tasman and Old Ironsides: Day and night work, January 27-28, 2018

Reroute of Downtown San Jose Lines: due to Women's March 1/20

Temporary Bus Stop Closure on Santa Clara Street at 7th: Bus stop at Santa Clara & 7th Street to be closed temporarily for construction.

Road Lane Closures on E Brokaw Rd. at N First Street, January 16-22, 2018: E Brokaw Rd. Rail Repair and Lane Closures at N First Street, Day and Night from January 16-22, 2018