I-280/I-880/Stevens Creek Boulevard Improvements Project
Improvements are coming to the 280 / 880 / Stevens Creek Blvd. interchanges! The project began construction in late Fall 2012 and is estimated to be completed in late 2014. The purpose of this project is to improve safety and traffic flow on the freeways and local roadways in the vicinity.
Project Description
The project proposes to improve traffic flow, safety and access between the Interstate 280 (I-280) and Interstate 880 (I-880) freeway corridors near Stevens Creek Boulevard, including modifications to the freeway-to-freeway intersection of State Route 17 (SR-17)/I-280/I-880 freeway interchange, as well as the adjacent interchanges at I-880/Stevens Creek Boulevard.
Specific improvements include:
-
Reconfiguring the existing full cloverleaf I-880/Stevens Creek Boulevard interchange to improve traffic flow in the surrounding interchange area by widening and realigning ramps, widening the overcrossing structure at Stevens Creek Boulevard over I-880, improving intersections and providing enhanced access for pedestrians and bicyclists.
-
Separating freeway-to-freeway traffic from local traffic by constructing a new direct connector from northbound I-280 to northbound I-880.
-
Constructing direct off ramps to Monroe Street from Southbound I-880.
Objective
To improve overall safety and traffic flow, enhance pedestrian friendly features along Stevens Creek Blvd., separate regional freeway-to-freeway traffic from local traffic and reduce queuing and traffic backups onto northbound I-280 from the connecting ramps to I-880 and Stevens Creek Blvd.

Fact Sheets, Environmental Reports and Documents
Fact Sheets (pdf)
More Information
Operations
Upon completion, Caltrans will operate and maintain the improved highway interchanges. The City of San Jose will operate and maintain the local streets outside of Caltrans right-of-way limits.
Capital Cost/Project Funding
$62.1 million from a combination of federal, CMIA, City of San Jose, and VTA funds have been designated for the project.
Project Schedule
| Design: |
Mid 2012
|
| Right of Way: |
Mid 2012 |
| Construction Start: |
Fall 2012 |
| Expected Completion |
Late 2014 |
Environmental Milestones:
| Draft Environmental Document Circulation: |
April 18, 2011 to May 18, 2011 |
| Final Environmental Document: |
Summer 2011 |