Downtown East Valley Preferred Investment Strategy
Steps Towards Implementation


August 2000 Complete MIS
August - December 2002 Conceptual Engineering completed
March - June 2003 Environmental Compliance completed
July - October 2003 Preliminary Engineering completed
July - December 2004 Acquire R/W
October - December 2004 Final Design completed
December 2004 - July 2007 Construction completed