State Route (SR) 152/156 Improvement Project

Overview
This project will reconfigure the State Route (SR) 152/156
intersection in southern Santa Clara County from an at-grade to a grade-separated intersection.
Project Objective
To provide operational and safety improvements at the SR 152/156 intersection by grade separating the left-turn movement from westbound SR 152 to westbound SR 156 and eliminating conflicting traffic movements.
Project Features
- Construction of a one-lane elevated flyover structure (overpass) for eastbound SR 152 traffic.
- Construction of a ground-level eastbound SR 152 to westbound SR 156 connector ramp.
- Additionally, the roadway between westbound SR 152 and westbound SR 156 will be reconstructed, as will the eastbound and westbound lanes of SR 152.
- Eastbound SR 156 to westbound SR 152 traffic will exit the highway at
Casa de Fruta Parkway and then merge onto westbound SR 152.
- Rehabilitation and restoration of landscaping within the intersection area
Maintenance of Traffic Flow
For the safety of the public and construction workers, traffic control measures (such as temporary lane closures and detours) will be used when needed. Contractors will make every effort to maintain access and minimize disruptions.
Operations
Upon completion, Caltrans will operate and maintain the highway improvements.
Capital Cost/ Project Funding
$34.8 million: The project funding is a combination of $6 million in local funds, $11.45 million in state funds, and $17.35 million in federal funds.
Project Schedule
Construction begins: May 2007
Project complete: spring 2009
How to Reach Us
For more information on this project, please contact VTA Community Outreach