Environmental Public Hearings
|
December 1999
|
|
Engineering/Design Phase
|
Complete December 2001
|
|
Final Environmental Impact Report (FEIR) Certification
|
May 2000
|
|
Property Acquisition
|
Complete June 2001
|
|
Advertise & Award Civil Construction Contracts
|
May 2001 - November 2001
|
|
Construction
|
May 2001 - Winter 2005
|
|
Diridon Tunnel (light rail and pedestrian)
|
Complete May 2003
|
|
San Jose Downtown Segment (Woz Way to San Jose Diridon Station)
|
Complete September 2003
|
|
Railroad Segment (San Jose Diridon to Winchester Station)
|
May 2001 - July 2004
|
|
Hamilton Avenue and Highway 17 Railroad Structures
|
September 2003 - September 2004
|
|
Vasona Stations
|
September 2003 - February 2005
|
|
Southwest Expressway Pedestrian Improvements
|
Complete December 2003
|
|
Systems/Signals/Overhead Contact System
|
September 2002 - Summer 2005
|
|
VTA Operations Turn-over and Testing
|
January 2005
|
|
Revenue Service Begins
|
Fall 2005
|