WHEN: Saturday, April 18, 2020, 2:00 AM through Monday, April 20, 2020, 4:00 AM Weather, scheduling, and conditions permitting.
WHAT: Drainage relocation, concrete foundation, and signal work at VTA light rail tracks.
VTA TRANSIT IMPACTS:Weekend bus bridge will be in place April 18-19, between Alder and Hostetter stations. Details at https://www.vta.org/go/service-alerts
COMMUNITY IMPACTS: Traffic control measures including street/lane closures, detours, and sidewalk closures will be in place. Please use extra caution in the construction zone and be aware of flagmen, signage, barricades, and cones. There will be noise, lights, dust, and construction vehicles driving forward and in reverse with the accompanying beeping noise that is required by OSHA for safety.