Day and Night Work (6/3-6/28): Capitol Expressway between Ocala Ave and Story Rd, and other intersections.

Notice Cause
Construction
Notice Effect(s)
Noise
Noise and Vibration
Traffic Delays
Start Date
End Date
What

DATES & TIMES:

  • Day: June 3 - June 28, 2024. between 8:00 a.m. to 5:00 p.m.
  • Night: June 3 - June 14, 2024, between 8:00 p.m. to 6:00 a.m

LOCATION: Capitol Expressway between Ocala Ave and Story Rd, and other intersections.

Why

ACTIVITIES:

  • Day: K-Rail, demolition, mobilize equipment, drilling, and pile testing, and fabricate temporary sound walls.
  • Night: Install temporary sound walls.

Community Impacts

POTENTIAL IMPACTS: Noise, vibration, traffic congestion.

Traffic Impacts

TRAFFIC CONTROL: Speed limit reduced to 35 mph. Temporary Lane closures.