Notice Cause
              Construction
          Notice Effect(s)
          Noise
          Noise and Vibration
          Traffic Delays
              Start Date
              End Date
              What
              DATES & TIMES:
- Day: June 3 - June 28, 2024. between 8:00 a.m. to 5:00 p.m.
- Night: June 3 - June 14, 2024, between 8:00 p.m. to 6:00 a.m
LOCATION: Capitol Expressway between Ocala Ave and Story Rd, and other intersections.
Why
              ACTIVITIES:
- Day: K-Rail, demolition, mobilize equipment, drilling, and pile testing, and fabricate temporary sound walls.
- Night: Install temporary sound walls.
Community Impacts
              POTENTIAL IMPACTS: Noise, vibration, traffic congestion.
Traffic Impacts
              TRAFFIC CONTROL: Speed limit reduced to 35 mph. Temporary Lane closures.