Notice Cause
Construction
Notice Effect(s)
Lane Closure
Noise
Traffic Delays
Start Date
End Date
What
Crews will be removing falsework from the Superstructure over the median. To do this, crews will be closing 2 lanes along NB Capitol Expressway, between Ocala Avenue to Capitol Avenue.
Why
Crews require space to stage cranes and other heavy machinery used to remove the falsework.
Detour
None.
Community Impacts
Adjacent community members may hear construction noises, including voices, hammering, items dropping/clanging, and backup alarms from heavy equipment. Residents may also see lights necessary to illuminate the worksite.
Service Impacts
None.
Traffic Impacts
Travel delays due to lane closures.
Pedestrian Impacts
Travel delays due to detours.
Bicycle Impacts
Travel delays due to detours.