EBRC Intersection Closure - Cunningham Ave & Capitol Expy. (2/3 - 2/4)

Notice Cause
Construction
Notice Effect(s)
Detour
Lane Closure
Noise
Traffic Delays
Start Date
End Date
Why

Crews will be pouring concrete onto the bridge structure above the intersection.

The Cunningham Avenue & Capitol Expressway intersection will be closed to through traffic in the east and westbound directions. A single lane will be open in the north and southbound directions.

Detour

Use either Tully Road or Ocala Avenue to U-turn onto Cunningham Avenue.

Community Impacts

Adjacent community members may hear construction noises, including voices,
items dropping, and back-up alarms. Residents may also see lights, necessary to illuminate the worksite.

Service Impacts

Slight arrival delays due to slowed traffic. Call VTA Customer Service for trip planning support: (408)321-2300

Traffic Impacts

Travel delays due to detours.
 

Pedestrian Impacts

None.

Bicycle Impacts

None.