Late-night to Early-morning full freeway closure beginning 1/25 to 2/1, at the US 101/Blossom Hill Road Overcrossing

Notice Cause
Construction
Start Date
End Date
What
Complete Freeway Closure on US 101 at Blossom Hill Road, 1/25 to 2/1

Freeway US 101 at Blossom Hill Road is subject to full freeway closure beginning 1/25 to 2/1 nightly, for the erection of falsework (temporary support structure for the bridge) of the US 101/Blossom Hill Road overcrossing. Construction is anticipated every night consecutively depending on progress. Tentatively, work is scheduled on weekdays but weekend work may be needed. Changeable message signs and directional signs will be in place to assist motorists traveling in the area. Please follow posted detour information.

Southbound US 101 closure from 1/25-1/27, between 12:00 AM to 5:00 AM

  • Closure of southbound (SB) lanes will start at Hellyer Ave. until all lanes are closed approaching Blossom Hill Rd., except the off-ramp.
  • Detour - SB 101 traffic will exit at Blossom Hill Rd off-ramp, turn left at Blossom Hill and then turn right onto SB 101 on-ramp.

Northbound US 101 closure from 1/27-2/1, between 11:00 PM to 4:00 AM

  • Closure of northbound (NB) lanes will start at Bernal Rd. until all lanes are closed approaching Blossom Hill Rd., except the off-ramp.
  • Detour - NB 101 traffic will exit at Blossom Hill Rd off-ramp, turn left at Blossom Hill and then turn right onto NB 101 on-ramp.