Ongoing Construction Activities (Now through early August)

Notice Cause
Construction
Notice Effect(s)
Detour
Lane Closure
Noise
Noise and Vibration
Traffic Delays
Start Date
End Date
Why

VTA, in partnership with Caltrans, continues construction on Phase 1 of the US 101/SR 25 Interchange Improvement Project. Motorists traveling through Gilroy and San Benito County should expect the following activities and impacts:

Night Work & Temporary Ramp Closures: Thursday, August 7 through Friday, August 8

Ongoing Construction Activities (Now through early August):

  • Demolition and cleanup at the Garlic Shoppe site (near NB US 101 On-Ramp) continues through August 1.
  • Tree removal is underway in areas previously protected due to nesting birds.
  • Permanent signage installation (West side of project) scheduled for August 4–6, helping guide drivers around the permanent closure of 101 on- and off-ramps at Castro Valley Rd and Mesa Rd.
  • Retaining wall construction continues near the future SR 25 connector. This includes:
    • Spraying concrete (shotcrete)
    • Rebar installation
    • Anchor/nail drilling
  • Drainage installation has resumed following environmental clearance.
  • Pile driving and bridge foundation work are ongoing near SR 25.

Active Work Zones:

  • Northbound US 101 ramps (near Garlic Shoppe)
  • SR 25 connector and bridge foundation area
  • Retaining wall adjacent to the SR 25 on-ramp to SB US 101

      hank you for your patience during this important work to improve traffic safety and regional mobility between Gilroy and Hollister.

      Stay informed: www.vta.org/SR25

      Detour

      For SB US 101 Off-Ramp to SR 25 Closure:

      ➡ Continue on SB US 101 past closed ramp
      ➡ Exit at Betabel Rd, turn left
      ➡ Enter NB US 101, then exit to SR 25

      For NB SR 25 to SB US 101 Closure:

      ➡ Turn left on Castro Valley Rd
      ➡ Continue east past Mesa Rd & Bolsa Rd
      ➡ Turn right on Monterey Rd
      ➡ Merge onto SB US 101 On-Ramp

      Community Impacts

      What to Expect:

      • Daytime noise (demolition, pile driving)
      • Construction crews working Monday through Saturday
      Service Impacts

      None

      Traffic Impacts

      Night Work & Temporary Ramp Closures:

      Thursday, August 7 (into Friday):

      • 6:00 PM–9:00 AM: SB US 101 On-Ramp from SR 25 – CLOSED
      • 9:00 PM–5:00 AM: SB US 101 Off-Ramp to SR 25 – CLOSED

      Friday, August 8 (into Saturday):

      • 6:00 PM–9:00 AM: SB US 101 On-Ramp from SR 25 – CLOSED
      • 10:00 PM–5:00 AM: SB US 101 Off-Ramp to SR 25 – CLOSED
      Pedestrian Impacts

      None

      Bicycle Impacts

      None