Utility Investigations at Stockton and Schiele Avenues - 11/16-11/25

Notice Cause
Utility Relocation
Start Date
End Date
What

VTA will be conducting utility investigations for the BART Phase II Project. 

What to Expect:

Investigations to verify utility locations on Stockton and Schiele Avenues. 

Location:

On Stockton Avenue, between Villa Avenue and Harding Avenue, and Schiele Avenue at Stockton Avenue, as shown on the map.

Approximate Start Date and Duration of Work:

November 16 – November 25, 2020

Up to two weeks in the area shown on the map.

General Work Hours:

9 a.m. – 3 p.m., Monday – Friday

No weekend work is anticipated.

Impacts:

At least one lane of traffic will be open at all times where the work is being performed. Work area will be restored once work is complete.

Parking will be impacted.

Neighbors can expect noise and vibrations during working hours.