Notice Cause
Construction
Start Date
End Date
What
Geotechnical Investigations Work at Cinnabar Street
What
Subsurface explorations/ borings to assess soil conditions
Where
On the northern side of Cinnabar Street between N. Morrison Ave and Stockton Ave.
When
June 15 – June 19, 2020
8 a.m. – 4:15 p.m., Monday – Friday
No weekend work anticipated
What to Expect
- At least one lane of traffic will always be open during construction activities
- Loss of some parking
- Minor dust, noise and vibration during work hours
- Restoration work (e.g. patching roads and pavement) after
Please Note:
VTA, as a transit agency, is considered an essential service. This geotechnical work will continue through the shelter in place order, and all workers will maintain the recommended six foot social distancing policy. For more information on VTA's COVID-19 response, please visit our website at: https://www.vta.org/covid-19