Notice of Construction on N. Montgomery Ave. 4/8/24 – 5/31/24

Notice Cause
Construction
Notice Effect(s)
Noise
Partial Parking Lot Closure
Start Date
End Date
What

Contractors will be preparing the site for directional boring and trench installation 

Where

The work will take place on N. Montgomery St. from Julian St. to Cinnabar St.

Diridon geo tech activity

When

  • Work will be conducted as early as Mon. April 8 – Fri. May 31.
  • General working hours will be 7:00 AM-5:00 PM. No weekend work is planned. Work hours will change from 9:30AM to 3:30PM pending SAP Center Event Calendar.

* Please note that timelines for construction activity have some inherent uncertainty and may change depending on field conditions and/or inclement weather.

What to Expect

  • The work activity will include construction equipment on site, periodic sidewalk closures, and lane closures. 
  • Workers will mark utility lines, excavate potholes, backfill excavations, and restore the lanes to original or better condition. 
  • This work activity does not typically generate dust.
  • Partial parking will be impacted by this work.
  • There will also be periodic, repetitive hammering during excavation.
Why

Necessary to help prepare for VTA’s BART Silicon Valley Phase II Project.   

Community Impacts

None.