Notice Cause
Construction
Notice Effect(s)
Noise
Noise and Vibration
Start Date
End Date
What
- Contractors will be collecting soil samples and installing groundwater monitoring instruments around the future Downtown San José Station.
Where
- The work will take place along North 30th Street between East Saint James Street and 5 Wounds Lane.
When*
- Work will be conducted as early as Monday, October 16 – Thursday, November 9
- General working hours will be 8:00AM-4:30 PM.
* Please note that timelines for construction activity have some inherent uncertainty and may change depending on field conditions and/or inclement weather.
What To Expect
- The work activity will be advanced with a truck-mounted, mud rotary drill rig.
- There will also be periodic, repetitive hammering during soil sampling.
- This work activity does not typically generate dust.
- Partial parking will be impacted by this work.
*All work has received necessary approvals and permits. Construction is a dynamic process and information is subject to change without notice.
Why
This work is necessary to help prepare for VTA’s BART Silicon Valley Phase II Project.
Community Impacts
None