Notice Cause
              Construction
          Notice Effect(s)
          Noise
          Noise and Vibration
              Start Date
              End Date
              What
              Contractors will be conducting geotechnical explorations.
Where
The work will take place on VTA property for the future Newhall Yard Maintenance Facility.
WHEN*
- Work will be conducted as early as Wed. Nov. 22 – Fri. Dec. 8
- General working hours will be 7:00AM-5:00 PM.
* Please note that timelines for construction activity have some inherent uncertainty and may change depending on field conditions and/or inclement weather.
What to Expect
Two contractor crews will perform the following work activities concurrently for the duration of work (this work activity does not typically generate dust):
- Cone Penetrometer Testing, which is self-contained activity within a panel truck.
- Truck-mounted mud rotary drilling. There will be periodic, repetitive hammering during soil sampling.
Why
              This work is necessary to help prepare for VTA’s BART Silicon Valley Phase II Project.
Community Impacts
              None.