What
Night Work & Lane Closures: March 23–27, 2026
When to Expect Impacts
- Monday, March 23 through Friday, March 27
- Nightly work hours, between 8:00 pm – 6:00 am(exact times may vary)
Traffic Impacts
Motorists should expect:
- Intermittent nighttime lane closures on US 101 and SR 25
- Impacts near the southbound US 101 off-ramp to SR 25
- Reduced lanes and brief delays through active work zones
Type of Work
- Roadway excavation and grading
- Guardrail repair and replacement near US 101 ramps
- Lane striping on SR 25
- Ongoing bridge construction
Why
VTA advises motorists of nighttime construction activities and lane closures at the US 101 / SR 25 interchange in Gilroy.
Work Locations
- US 101 near the SR 25 interchange
- Southbound US 101 off-ramp to SR 25
- SR 25 (eastbound and westbound)
- Areas near ongoing bridge construction (connector structures)
Detour
Detour Routes
Detour Route for Overnight closure of the US 101 southbound on-ramp:
- Continue north on SR 25
- Follow detour signs onto Monterey Road
- Reconnect to southbound US 101 at the Monterey Road interchange
Detour Route for Overnight closure of the US 101 southbound off-ramp:
- Continue South on US 101 to Betabel Road
- Betabel Road to Northbound US 101
- Northbound US 101 to Southbound SR 25
Community Impacts
What Drivers Should Know
- Allow extra travel time when traveling at night
- Follow posted detours and signage
- Watch for construction crews and equipment
- Expect noise and lighting in the work area during nighttime hours
Stay Informed
Traffic conditions may change due to weather or construction. For updates, visit https://www.vta.org/projects/us-101sr-25-interchange-phase-1 | Contact VTA Community Outreach at (408) 321-7575 or Email community.outreach@vta.org.
Traffic Impacts
Detours
VTA will have ongoing overnight ramp closures at the US 101/SR 25 Interchange beginning next week as part of ongoing construction improvements. Closures will continue into the following week.
Starting Monday, March 23, at 8:00 pm.
The following ramps will be closed overnight:
- Southbound US 101 on-ramp from SR 25
- Southbound US 101 off-ramp to SR 25
All ramps are expected to reopen by 6:00 AM each morning.