Overview
Santa Clara Valley Transportation Authority (VTA) is investing in rehabilitation and modernization projects across maintenance yards to improve employee wellbeing and workplace functionality. Planned upgrades focus on employee spaces including kitchens, restrooms, locker rooms, break areas, and outdoor amenities. Electric vehicle (EV) chargers will also be installed at all yards. Some construction projects are already underway, while others are scheduled to begin over the next several months. Procurement and construction schedules are dynamic and timelines may change.
Funding
- Funding for these upgrades is provided through the Transit Oriented Development Budget
- Funding for Guard House improvements at Guadalupe Yard is provided through SB129
- Yard Facility Improvements (Almaden $25M)
Project Updates by Location
Cerone Yard
Building B
- Timekeepers offices, dispatch, break area, restrooms, conference room and outdoor area improvements
- Construction started: Spring 2026
- Estimated completion: Fall 2026
Building G
- Restroom, breakroom, and locker room upgrades
Building F
- New breakroom with kitchenette, lactation facility and restrooms
- Boiler room conversion
Chaboya Yard
Building A/B
- Breakroom and restroom upgrades, pergola installation outside training room, and office reconfiguration
- Construction scheduled to begin: Spring 2027
- Duration: Approximately 8 months
Building C
- Foreman's area, bathrooms, shower, locker room upgrades
- Breakroom improvements
- Construction scheduled to begin: Fall 2026
- Duration: Approximately 6 months
Building E (Fuel Island)
- Restroom upgrades and breakroom upgrades
- Construction scheduled to begin: End of Summer 2026
North Yard
Building A
- New kitchenette and finish upgrades planned
- Construction scheduled: Late Summer 2026
- Duration: Approximately 3 months
- Completion target: December 2026
Guadalupe Yard
Guard House
- Fire Department review completed
- Construction starts: Winter 2026
- Estimated completion: Fall 2027
- Gas line relocation to be complete end of August
Building A
- First floor restroom and kitchenette replacement
- Project Completed: 2025
Memorial Garden Plaques
- Project Completed: Spring 2026
EV Chargers Update and Schedule
Multiple coordination meetings with Operations have taken place, and future charger locations are nearly finalized. Conceptual design is complete, and we anticipate finalizing designs are approximately four chargers (eight stalls) at each yard by October 2026. Following design completion, the projects will move into the procurement phase.
Furniture, Gyms, and HVAC POs
VTA is enhancing gym facilities throughout its yards to provide employees with refreshed, more comfortable spaces for health and wellness. Improvements include new paint, upgraded lighting, ceiling fans, and new fitness equipment. These upgrades are part of VTA's ongoing commitment to improving employee facilities and supporting a healthier workplace. Chaboya Building A and C will begin HVAC equipment upgrades and duct cleaning. This will begin during Fall 2026.